  • Update: Capital Projects Progress as of 9/15/23
    The Mountain Ops team has continued its hard work, installing the high-efficiency snowmaking system throughout one of the rainiest summers on record. Even with the challenges, the team's determination has allowed the project to stay on track. It’s been a busy summer at Sugarloaf, continue to check back for more updates.
  • Update: Capital Projects Progress as of 8/7/23
    120 acres of new skiable terrain have been cut, concrete bases poured for the new high-speed lift – The Bucksaw Express, 246 high-efficiency HKD snow guns and over 88,000’ of snowmaking pipe are being installed.  
  • Update: Capital Projects Progress as of 4/18/23
    The first phase of Sugarloaf’s West Mountain Development is underway with logging progress on 12 new ski trails and first neighborhood of 20 single-family lots.  
  • Update: Capital Projects Progress as of 10/26/22
    Construction of the new T-bar on Competition Hill continues with the pouring of concrete and installation of towers. Learn more here. 
  • Update: Capital Projects Progress as of 10/5/22
    In preparation for winter, progress continues around the mountain. Construction of the new T-bar on Competition Hill is currently underway, and the completion of a new booster pump house located near Bullwinkles will allow for an increased number of snow guns to run simultaneously. Learn more here.